Two playgrounds destroyed by falling trees — Smoke Rise and Rock Spray — need replacing at about $60,000 each, and a larger list of aging playgrounds totals $1.25 million. Council agreed to move ahead with Braylon, Battery Way, and the two storm-damaged lots, holding the rest until SPLOST funds are clearer after fire stations and other projects.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Aug 27, 2026.
Impact analysis
About $1.25 million for the full list, with roughly $1.2 million in SPLOST playground money available — council wants to protect funds for fire stations.
Kids and families in neighborhoods getting new playgrounds — usage typically jumps after a rebuild.
Residents near lower-priority tot lots may wait years for upgrades.
Mentions & discussions (2)
City Council - Aug 27, 2026
Two playgrounds destroyed by falling trees — Smoke Rise and Rock Spray — need replacing at about $60,000 each, and a larger list of aging playgrounds totals $1.25 million. Council agreed to move ahead with Braylon, Battery Way, and the two storm-damaged lots, holding the rest until SPLOST funds are clearer after fire stations and other projects.
City Council - Jun 4, 2026
Staff showed playground designs from $500K to $1M plus a first-in-Georgia ninja course (~$560K). Council consensus favors the $630K poured-surface playground plus the ninja course — roughly $1.19M from SPLOST — with final selection expected at a future meeting.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Peachtree City
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.